Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | kick-off done | 2024-04-18 |
| |
M1 (Commonalities & ICM) | Commonalities: alpha available ICM: alpha / M1 skipped | 2024-06-10 | M1 was declared to be for Commonalities only by the TSC on 2024-07-04. | |
M2 (Commonalities & ICM) | Commonalities: release PR ready ICM: release PR ready | 2024-07-11 | Commonalities 0.4.0-rc.1 and ICM 0.2.0-rc.1 - approved on 2024-07-10. ICM 0.2.0-rc.2 released on 2024-08-01 | |
M3 (Sub Projects) | Preparation of first release-candidates by M3 (through one or more alpha API versions as needed) | Prepare your release PR by this date and have it reviewed by the Release Mgmt team before merging. Last submission date for M3 review: Aug 10th (for approval by Aug 15th) | ||
M4 (Sub Projects) | 08-30 | APIs that passed M3 (or submitted for approval) can start to prepare their public release PR for M4. | ||
M5 | 09-15 | |||
M6 | 09-30 |
...
Working Group | Commonalities | ICM |
---|---|---|
Target version | 0.4.0 | 0.2.0 |
Target scope | Commonalities/issues/175 | IdentityAndConsentManagement/issues/146 |
M1 / date | 2024-06-10 | na |
M2 / date | 2024-07-11 | 2024-07-11 |
Pre-release tag | r0.4.0-rc.1 | v0r0.2.0-rc.12 |
M5 / date | yyyy-mm-dd | yyyy-mm-dd |
Public release tag | <release tag link> | <release tag link> |
...