Review closed (2024-04-30) - approved content move to Meta-release Milestones page. - this page is kept to resolve comments and will be archived.
UPDATED PROPOSAL FOR REVIEW (2024-04-23)
Please review the table on this page - proposal is that it replaces the table on the Meta-release Milestones page.
Milestone / start date | Actors & Actions for next milestone | Timeline | Week Nr |
---|
pre-M0 | Release Management - Prepare meta-release page
- Request TSC to declare kickoff
Commonalities & ICM (from previous M2) - Prepare release scope definition for meta-release.
- Implement scope in one or more alpha releases
TSC - Declare meta-release kickoff
|
|
|
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | Release Management - Send kick-off message to all@lists.camaraproject.org
- Once available, check the final alpha release of Commonalities & ICM and, if OK, submit to TSC for approval
- After TSC approval, announce M1 milestone
Commonalities & ICM - Define the scope for meta-release.
- Record scope in dedicated GitHub issue.
- Submit scope issue for TSC review
- Develop Commonalities & ICM scope through one or more alpha releases
- Update data in the meta-release plan with each alpha release
- Create final alpha release PR and submit to Release Management
- After TSC approval, create approved final alpha release for Commonalities & ICM
- Update the meta-release plan with the alpha release tag
TSC - Approve final alpha release PRs of Commonalities & ICM
| 2 weeks |
|
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | Commonalities & ICM - Fix bugs raised by users through one or more release-candidates
- Update release tracker on meta-release page with each release-candidate
- Create final release-candidate PR and submit to Release Management
- After TSC approval:
- Create the final release-candidate for Commonalities & ICM
- Update the meta-release page for Commonalities & ICM with release-candidate tag
Release Management - Check final release-candidate PRs of Commonalities and ICM and, if OK, submit to TSC for approval
- After TSC approval, and commit of Commonalities and ICM final release-candidate PRs, announce M2 milestone
TSC - Approve final release-candidate PRs of Commonalities & ICM
| 7 weeks |
|
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 | API Sub-projects - Create API release tracking page for the API if it does not yet exist
- Create API release tracker for the API version to be released
- Define scope of API release:
- Record scope in dedicated GitHub issue.
- Submit scope for TSC review
- Update the release tracker with the scope issue link
- Develop API scope through one or more alpha release(s)
- Update the API release tracker with each alpha release
- Create first release-candidate PR and submit to Release Management
- After Release Management approval:
- Create first release-candidate for the API
- Update the API release tracker with the release-candidate tag
Release Management, for each API - Once available, check the API release-candidate PR
- If OK, approve creation of first release-candidate
- If NOK, or in case of questions, notify TSC for checking the API release-candidate PR
- Announce M3 milestone with all approved API release-candidates.
TSC - Review API release-candidate PRs on request of Release Management and approve (or reject)
| 9 weeks |
|
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 | API Sub-projects - Fix bugs raised by API testers through one or more release-candidates
- Update API release tracker with each release-candidate
- Submit public-release PR to Release Management for checking
- After TSC approval:
- Create API public-release
- Update the API release tracker with public-release tag
Release Management - Once available, check API public-release PR and, if OK, submit to TSC for approval
- Announce M4 milestone when all API public-releases are approved by TSC
TSC - Approval of API public-release PR for all proposed APIs
| 9 weeks |
|
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API | Release Management - Check that all API release trackers are updated for the meta-release
- Propose meta-release content to TSC
- After TSC approval, publish the meta-release
- Announce the M5 meta-release on all@lists.camaraproject.org
TSC: | 2 weeks |
|
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 | Release Management - Review release process with all teams and identify areas for improvement.
- Propose improvements for TSC approval
TSC - Meta-release improvements approval.
| 2 weeks |
|
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
...