Milestone / start date

Actors & Actions for next milestone

Timeline

Week Nr

pre-M0

Release Management

  • Prepare meta-release page
  • Request TSC to declare kickoff

Commonalities & ICM (from previous M2)

  • Prepare release scope definition for meta-release.

TSC

  • Declare meta-release kickoff


M0 

Meta-release kickoff

M00
starts @ M0

Release Management (before M0)

Commonalities & ICM

  • Finalize release scope definition for meta-release.
    • Record scope in dedicated GitHub issue.
    • Submit scope issue for TSC review
  • Develop Commonalities & ICM scope through one or more alpha release(s)
  • Update data in the meta-release plan with each alpha release
  • Submit final alpha releases PRs for TSC review:
  • If OK: create final alpha release for Commonalities & ICM
  • Send Commonalitie & ICM alpha release message to release@lists.camaraproject.org

TSC

  • Review final alpha releases PRs of Commonalities & ICM
2 weeks

M1

Alpha Commonalities & ICMM0 + 2 weeks2
starts @ M1

Commonalities & ICM

  • Fix bugs raised by users through one or more release-candidates
  • Update release tracker on target meta-release page with each release-candidate
  • Submit final release-candidates PRs for TSC approval
  • If approved:
  • Create final release-candidates for Commonalities & ICM
  • Prepare public-release PR for Commonalities & ICM for M5

TSC

  • Approval of final release-candidates PRs of Commonalities & ICM
10 weeks

M2

Release-candidate Commonalities & ICMM1 + 10 weeks12

M1

Alpha Commonalities & ICMM0 + 2 weeks2
starts @ M1

API Sub-projects

  • Define scope of API release.
    • Record scope in dedicated GitHub issue.
    • Submit scope for TSC review
  • Create API release tracker for the API version
  • Develop API scope through one or more alpha release(s)
  • Update the API release tracker with each alpha release
  • Submit final alpha API release PR for TSC review:
  • If OK: create final alpha releases for the API

TSC

  • Review final alpha API release PR
8 weeks

M3

Alpha APIs

M1 + 8 weeks

10
starts @ M3

API Sub-projects

  • Fix bugs raised by API testers through one or more release-candidates
  • Update API release tracker with each release-candidate
  • Submit final API release-candidates PR for TSC approval
  • If approved:
    • Create final API release-candidate
    • Prepare API public-release PR for M5

TSC

  • Approval of final API release-candidate PR
10 weeks

M4

Release-candidate APIs

M3 + 10 weeks

20

starts @ M2 for Commonalities & ICM

starts @ public-release PR for an API

Release Management (this can start for each item, whenever the item public-release PR is made available)

  • For Commonalities and ICM, check that all release assets are available in the public-release PR
  • If OK: approve creation of public-release of Commonalities and ICM
  • For each API release-candidate, check that all release assets are available in the API public-release PR
  • Propose meta-release content to TSC
  • On TSC approval, 
    • notify approval on release@lists.camaraproject.org
    • notify Outreach Committee
    • publish the meta-release information
    • send meta-release announcement to all CAMARA 

TSC:

  • Meta-release approval

Commonalities & ICM

  • Publish new release through approved PR
  • Update public-release information on meta-release plan

API Sub-projects

  • Publish new API release through approved PR
  • Update API release tracker to reflect public-release API version & tag
2 weeks

M5

Meta-releaseM4 + 2 weeks22
starts @ M5

Release Management

  • Review release process with teams and identify areas for improvement. 
  • Propose improvements for TSC approval

TSC

  • Meta-release improvements approval.
2 weeks

M6

Post ReleaseM5 + 2 weeks24

...