CAMARA release management process requires each API Sub Project to plan and track their API releases so that meta-release can be planned.
...
Meta-release | The name of the meta-release, e.g. Fall24 |
API name | The API name. See the definition of API name on this page: API Release Process, e.g. geofencing |
Group | The name of the GitHub repository for the API Sub Project, e.g. DeviceLocation |
Repository | The shortened link to GitHub repository for the API Sub Project, e.g. DeviceLocation |
Target version | The API version that you plan to publish in the indicated meta-release, e.g. 1.0.0 |
Target scope | The shortened link to a GitHub issue called "Scope for target version" which needs to be created latest at M1 and resolved by M3 e.g. DeviceLocation/issues/58 |
Target maturity | Indicates the maturity of the API version that is targeted in the upcoming meta-release: choose one of initial / stable. |
Readiness checklist | The shortened link to the API readiness checklist for the API. The template of the checklist can be found here: (link to release management repo tbd) |
M3 date | The date when the first release-candidate API version is ready. This is the starting point for creating the final release-candidate API version for M4. After this date, only bug fixes and necessary non-breaking changes can be made to the API. Format is yyyy-mm-dd |
M4 date | The date when the final release-candidate API version for M5 submission is ready. This is the starting point for creating the public-release API version for M5. Once this date is provided by the API project team, the Release Management team can check the release-candidate API version for acceptance and submit to the TSC for approval. Format is yyyy-mm-dd |
API version | The version of the latest pre-release (alpha or release-candidate) API version to be updated at M3 and M4 date, e.g. 0.2.0_alpha.3, 0.10.0-rc.2, 0.10.1, 1.0.0-rc.5) |
pre-release tag | The shortened release tag of the latest pre-release (alpha or release-candidate) for the API version e.g. QualityOnDemand/releases/tag/r0.10 |
M5 date | The date by which the Release Management team has checked the release-candidate API version provided at the M4 date and the API is approved by the TSC. The link to the PR for public-release API version shall be included in this field when available After this date, if approval is obtained, the API Sub Project shall commit the PR of the public-release API version and its release assets for use in the meta-release. Format is yyyy-mm-dd. The link to the PR shall be removed after the commit is done. |
public-release tag | The shortened release tag of the public-release API version. This field is updated once the public-release has been created, e.g. QualityOnDemand/releases/tag/r1.0 |
Comments | Field for exchanging information with RM team, for example M3: alpha ready for RM M3: checked by RM - NOK - missing sunny test cases M4: ready for RM M4: ready for approval by TSC M4: approved by TSC M5: public-release done M5: API version retirement planned by yyyy-mm-dd. |
Contacts | Contact names for the API release: name1 @name2 |
...