Timeline
Meta-release milestone dates
...
Milestone dates
Milestone | Target date | Status | Actual date |
---|---|---|---|
M0 | 30/09 | scope definition |
|
M1 | 15/10 | ||
M2 | 31/12 | ||
M3 | 15/12 | ||
M4 | 28/02 | ||
M5 | 15/03 | ||
M6 | 31/03 |
Milestone | Target date | Status | Actual date |
---|---|---|---|
M0 | 15/04 | scope definition |
|
M1 | 30/04 | ||
M2 | 15/06 | ||
M3 | 15/06 | ||
M4 | 31/08 | ||
M5 | 15/09 | ||
M6 | 30/09 |