Milestone | Milestone Name | Actions to achieve next milestone | Timeline | Week number |
---|
Kickoff - M0 | Start of release cycle. |
| M0 | 0 |
|
| - Scope of Work Products clarified and recorded in dedicated issue.
- Identify commonalities work products.
- Create alpha release for Commonalities & ICM
- Create initial PRs for commonalities.
- Agree on the scope of commonalities.
- TSC review.
| 2 weeks |
|
M1 | Initiate Commonalities & ICM |
| M0 + 2 weeks | 2 |
|
| - Create release-candidate for Commonalities & ICM
- Prepare public-release for Commonalities & ICM.
- Complete initial PR reviews.
- TSC Approval.
| 10 weeks |
|
M2 | Finalize Commonalities & ICM |
| M1 + 10 weeks | 12 |
|
| - Scope Request to Sub-Projects / APIs.
- Determine requirements for Sub-projects / APIs.
- Create PRs for Sub-projects / APIs.
- Review and finalize PRs.
- Confirm scope of Sub-projects / APIs
- Define API test cases.
- Define acceptance criteria.
- Create alpha release for for Sub-projects / APIs.
| 8 weeks |
|
M3 | Initiate Sub-projects / APIs |
| M1 + 8 weeks | 10 |
|
| - Conduct testing and log test result.
- Evaluate and log acceptance criteria.
- Code Freeze
- Create release-candidate for Sub-Projects / APIs.
- Prepare public-release for Sub-Projects / APIs.
- Request approval of Sub-projects / APIs to Release Management WG for meta-release
| 10 weeks |
|
M4 | Finalize Sub-projects / APIs |
| M3 + 10 weeks | 20 |
|
| - Determine the acceptance of the release-candidates for inclusion in the meta-release
- Bundle & publish meta-release
- TSC Approval
- Publish meta-release
| 2 weeks |
|
M5 | Meta Release |
| M4 + 2 weeks | 22 |
|
| - Review release process and identify areas for improvement.
- Release Retro.
- TSC Approval.
| 2 weeks |
|
M6 | Post- Release |
| M5 + 2 weeks | 24 |
Commonalities Actions to achieve next milestone
Actions Commonalities & ICM |
---|
Actions to achieve next milestone
API Actions API Sub-projects | Timeline | Week |
---|
numberNr |
---|
Kickoff - M0 | Start of meta-release |
|
| M0 | 0 |
|
| - Scope of Work Products clarified and recorded in dedicated issue.
- Identify commonalities work products.
- Create alpha release for Commonalities & ICM
- Create initial PRs for commonalities.
- Agree on the scope of commonalities.
- TSC review.
|
| 2 weeks |
|
M1 | Initial Commonalities & ICM |
|
| M0 + 2 weeks | 2 |
|
| - Create release-candidate for Commonalities & ICM
- Prepare public-release for Commonalities & ICM.
- Complete initial PR reviews.
- TSC Approval.
|
| 10 weeks |
|
M2 | Final Commonalities & ICM |
|
| M1 + 10 weeks | 12 |
|
|
| - Scope Request to Sub-Projects / APIs.
- Determine requirements for Sub-projects / APIs.
- Create PRs for Sub-projects / APIs.
- Review and finalize PRs.
- Confirm scope of Sub-projects / APIs
- Define API test cases.
- Define acceptance criteria.
- Create alpha release for for Sub-projects / APIs.
| 8 weeks |
|
M3 | Initial Sub-projects / APIs |
|
| M1 + 8 weeks | 10 |
|
|
| - Conduct testing and log test result.
- Evaluate and log acceptance criteria.
- Code Freeze
- Create release-candidate for Sub-Projects / APIs.
- Prepare public-release for Sub-Projects / APIs.
- Request approval of Sub-projects / APIs to Release Management WG for meta-release
| 10 weeks |
|
M4 | Final Sub-projects / APIs |
|
| M3 + 10 weeks | 20 |
|
|
| - Determine the acceptance of the release-candidates for inclusion in the meta-release
- Bundle & publish meta-release
- TSC Approval
- Publish meta-release
| 2 weeks |
|
M5 | Meta Release |
|
| M4 + 2 weeks | 22 |
|
| - Review release process and identify areas for improvement.
- Release Retro.
- TSC Approval.
|
| 2 weeks |
|
M6 | Post Release |
|
| M5 + 2 weeks | 24 |
Milestone | Actions Commonalities & ICM | Actions API Sub-projects | Timeline | Week Nr |
---|
M0 - meta-release kickoff |
|
| M0 | 0 |
| - Scope of Work Products clarified and recorded in dedicated issue.
- Identify commonalities work products.
- Create alpha release for Commonalities & ICM
- Create initial PRs for commonalities.
- Agree on the scope of commonalities.
- TSC review.
|
| 2 weeks |
|
M1 - Initial Commonalities & ICM |
|
| M0 + 2 weeks | 2 |
| - Create release-candidate for Commonalities & ICM
- Prepare public-release for Commonalities & ICM.
- Complete initial PR reviews.
- TSC Approval.
|
| 10 weeks |
|
M2 - Final Commonalities & ICM |
|
| M1 + 10 weeks | 12 |
|
| - Scope Request to Sub-Projects / APIs.
- Determine requirements for Sub-projects / APIs.
- Create PRs for Sub-projects / APIs.
- Review and finalize PRs.
- Confirm scope of Sub-projects / APIs
- Define API test cases.
- Define acceptance criteria.
- Create alpha release for for Sub-projects / APIs.
| 8 weeks |
|
M3 - Initial Sub-projects / APIs |
|
| M1 + 8 weeks | 10 |
|
| - Conduct testing and log test result.
- Evaluate and log acceptance criteria.
- Code Freeze
- Create release-candidate for Sub-Projects / APIs.
- Prepare public-release for Sub-Projects / APIs.
- Request approval of Sub-projects / APIs to Release Management WG for meta-release
| 10 weeks |
|
M4 - Final Sub-projects / APIs |
|
| M3 + 10 weeks | 20 |
|
| - Determine the acceptance of the release-candidates for inclusion in the meta-release
- Bundle & publish meta-release
- TSC Approval
- Publish meta-release
| 2 weeks |
|
M5 - Meta Release |
|
| M4 + 2 weeks | 22 |
| - Review release process and identify areas for improvement.
- Release Retro.
- TSC Approval.
|
| 2 weeks |
|
M6 - Post Release |
|
| M5 + 2 weeks | 24 |
back to one action column
Milestone | Actors / Actions for next milestone | Timeline | Week Nr |
---|
M0 - meta-release kickoff | Release Management | M0 | 0 |
| Commonalities & ICM - Scope of Work Products clarified and recorded in dedicated issue.
- Identify commonalities work products.
- Create alpha release for Commonalities & ICM
- Create initial PRs for commonalities.
- Agree on the scope of commonalities.
- TSC review.
| 2 weeks |
|
M1 - Draft Commonalities & ICM |
| M0 + 2 weeks | 2 |
| Commonalities & ICM - Create release-candidate for Commonalities & ICM
- Prepare public-release for Commonalities & ICM.
- Complete initial PR reviews.
- TSC Approval.
| 10 weeks |
|
M2 - Final Commonalities & ICM |
| M1 + 10 weeks | 12 |
| - Scope Request to Sub-Projects / APIs.
- Determine requirements for Sub-projects / APIs.
- Create PRs for Sub-projects / APIs.
- Review and finalize PRs.
- Confirm scope of Sub-projects / APIs
- Define API test cases.
- Define acceptance criteria.
- Create alpha release for for Sub-projects / APIs.
| 8 weeks |
|
M3 - Draft APIs |
| M1 + 8 weeks | 10 |
| API Sub-projects - Conduct testing and log test result.
- Evaluate and log acceptance criteria.
- Code Freeze
- Create release-candidate for Sub-Projects / APIs.
- Prepare public-release for Sub-Projects / APIs.
- Request approval of Sub-projects / APIs to Release Management WG for meta-release
| 10 weeks |
|
M4 - Final APIs |
| M3 + 10 weeks | 20 |
| Release Management - Determine the acceptance of the release-candidates for inclusion in the meta-release
- Bundle & publish meta-release
- TSC Approval
- Publish meta-release
| 2 weeks |
|
M5 - Meta Release |
| M4 + 2 weeks | 22 |
| Release Management - Review release process and identify areas for improvement.
- Release Retro.
- TSC Approval.
| 2 weeks |
|
M6 - Post Release |
| M5 + 2 weeks | 24 |
Horizontal milestones
Entity | M0 | M1 (M0+2 weeks) | M2 (M1+10 weeks) | M3 | M4 | M5 | M6 |
---|
All | Kickoff |
|
|
|
|
|
|
Commonalities & ICM |
| - Scope of Work Products clarified and recorded in dedicated issue.
- Identify commonalities work products.
- Create alpha release for Commonalities & ICM
- Create initial PRs for commonalities.
- Agree on the scope of commonalities.
- TSC review.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
...