MilestoneMilestone NameActions to achieve next milestone

Timeline

Week number

Kickoff - M0Start of release cycle.
M00


  • Scope of Work Products clarified  and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities & ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.
2 weeks

M1

Initiate Commonalities & ICM
M0 + 2 weeks2


  • Create release-candidate for Commonalities & ICM
  • Prepare public-release for Commonalities & ICM.
  • Complete initial PR reviews.
  • TSC Approval.
10 weeks

M2

Finalize Commonalities & ICM
M1 + 10 weeks12


  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for Sub-projects / APIs.
  • Create PRs for Sub-projects / APIs.
  • Review and finalize PRs.
  • Confirm scope of Sub-projects / APIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Create alpha release for for Sub-projects / APIs.
8 weeks

M3

Initiate Sub-projects / APIs

M1 + 8 weeks

10


  • Conduct testing and log test result.
  • Evaluate and log acceptance criteria.
  • Code Freeze
  • Create release-candidate for Sub-Projects / APIs.
  • Prepare public-release for Sub-Projects / APIs.
  • Request approval of Sub-projects / APIs to Release Management WG for meta-release
10 weeks

M4

Finalize Sub-projects / APIs

M3 + 10 weeks

20


  • Determine the acceptance of the release-candidates for inclusion in the meta-release
  • Bundle & publish meta-release
  • TSC Approval
  • Publish meta-release
2 weeks

M5

Meta Release
M4 + 2 weeks22


  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.
2 weeks

M6

Post- Release
M5 + 2 weeks24



Commonalities
MilestoneMilestone Name

Actions to achieve next milestone

Actions Commonalities & ICM

Actions to achieve next milestone

API

Actions API Sub-projects

Timeline

Week

number

Nr

Kickoff - M0Start of meta-release

M00


  • Scope of Work Products clarified  and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities & ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.

2 weeks

M1

Initial Commonalities & ICM

M0 + 2 weeks2


  • Create release-candidate for Commonalities & ICM
  • Prepare public-release for Commonalities & ICM.
  • Complete initial PR reviews.
  • TSC Approval.

10 weeks

M2

Final Commonalities & ICM

M1 + 10 weeks12



  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for Sub-projects / APIs.
  • Create PRs for Sub-projects / APIs.
  • Review and finalize PRs.
  • Confirm scope of Sub-projects / APIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Create alpha release for for Sub-projects / APIs.
8 weeks

M3

Initial Sub-projects / APIs


M1 + 8 weeks

10



  • Conduct testing and log test result.
  • Evaluate and log acceptance criteria.
  • Code Freeze
  • Create release-candidate for Sub-Projects / APIs.
  • Prepare public-release for Sub-Projects / APIs.
  • Request approval of Sub-projects / APIs to Release Management WG for meta-release
10 weeks

M4

Final Sub-projects / APIs


M3 + 10 weeks

20



  • Determine the acceptance of the release-candidates for inclusion in the meta-release
  • Bundle & publish meta-release
  • TSC Approval
  • Publish meta-release
2 weeks

M5

Meta Release

M4 + 2 weeks22


  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.

2 weeks

M6

Post Release

M5 + 2 weeks24





Milestone

Actions Commonalities & ICM

Actions API Sub-projects

Timeline

Week Nr

M0 - meta-release kickoff

M00

  • Scope of Work Products clarified and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities & ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.

2 weeks

M1 - Initial Commonalities & ICM



M0 + 2 weeks2

  • Create release-candidate for Commonalities & ICM
  • Prepare public-release for Commonalities & ICM.
  • Complete initial PR reviews.
  • TSC Approval.

10 weeks

M2 - Final   Commonalities & ICM



M1 + 10 weeks12


  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for Sub-projects / APIs.
  • Create PRs for Sub-projects / APIs.
  • Review and finalize PRs.
  • Confirm scope of Sub-projects / APIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Create alpha release for for Sub-projects / APIs.
8 weeks

M3 - Initial                  Sub-projects / APIs



M1 + 8 weeks

10


  • Conduct testing and log test result.
  • Evaluate and log acceptance criteria.
  • Code Freeze
  • Create release-candidate for Sub-Projects / APIs.
  • Prepare public-release for Sub-Projects / APIs.
  • Request approval of Sub-projects / APIs to Release Management WG for meta-release
10 weeks

M4 - Final                    Sub-projects / APIs



M3 + 10 weeks

20


  • Determine the acceptance of the release-candidates for inclusion in the meta-release
  • Bundle & publish meta-release
  • TSC Approval
  • Publish meta-release
2 weeks

M5 - Meta Release



M4 + 2 weeks22

  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.

2 weeks

M6 - Post Release



M5 + 2 weeks24


back to one action column

Milestone

Actors / Actions for next milestone

Timeline

Week Nr

M0 - meta-release kickoff

Release Management

M00

Commonalities & ICM

  • Scope of Work Products clarified and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities & ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.
2 weeks

M1 - Draft Commonalities & ICM


M0 + 2 weeks2

Commonalities & ICM

  • Create release-candidate for Commonalities & ICM
  • Prepare public-release for Commonalities & ICM.
  • Complete initial PR reviews.
  • TSC Approval.
10 weeks

M2 - Final Commonalities & ICM


M1 + 10 weeks12

  • Scope Request to Sub-Projects / APIs.
  • Determine requirements for Sub-projects / APIs.
  • Create PRs for Sub-projects / APIs.
  • Review and finalize PRs.
  • Confirm scope of Sub-projects / APIs 
  • Define API test cases.
  • Define acceptance criteria.
  • Create alpha release for for Sub-projects / APIs.
8 weeks

M3 - Draft APIs


M1 + 8 weeks

10

API Sub-projects

  • Conduct testing and log test result.
  • Evaluate and log acceptance criteria.
  • Code Freeze
  • Create release-candidate for Sub-Projects / APIs.
  • Prepare public-release for Sub-Projects / APIs.
  • Request approval of Sub-projects / APIs to Release Management WG for meta-release
10 weeks

M4 - Final APIs


M3 + 10 weeks

20

Release Management

  • Determine the acceptance of the release-candidates for inclusion in the meta-release
  • Bundle & publish meta-release
  • TSC Approval
  • Publish meta-release
2 weeks

M5 - Meta Release


M4 + 2 weeks22

Release Management

  • Review release process and identify areas for improvement. 
  • Release Retro.
    • Inputs from Sub Projects
  • TSC Approval.
2 weeks

M6 - Post Release


M5 + 2 weeks24




Horizontal milestones

EntityM0M1 (M0+2 weeks)M2 (M1+10 weeks)M3M4M5M6
AllKickoff





Commonalities & ICM
  • Scope of Work Products clarified  and recorded in dedicated issue.
  • Identify commonalities work products.
  • Create alpha release for Commonalities & ICM
  • Create initial PRs for commonalities.
  • Agree on the scope of commonalities.
  • TSC review.





































...