The actual milestone dates and status shall be updated on the meta-release plan when the milestone is achieved.
...
Milestone status
The overall milestone status is reflected by the milestone status table on the meta-release plan. Its content is managed by the Release Management team and shall have values defined as follows:
Milestone | Before milestone | After milestone |
---|---|---|
M0 | kick-off preparation | kick-off done |
M1 | alpha PR | alpha for M2 |
M2 | release-candidate PR | release-candidate for M4 |
M3 | API first release-candidate PR | API first release-candidate for M4 |
M4 | API final release-candidate PR API public-release PR | API final release-candidate API public-release for M5 |
M5 | meta-release preparation | meta-release published |
M6 | retrospective preparation | retrospective done |
Commonalities and ICM
The Commonalities and ICM teams shall respectively update and maintain their information on the meta-release page following the below steps.
...