Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • In the page title, change <meta-release name> to the actual meta-release name (e.g. Fall25, Spring26, etc).
  • At the top of the page, click the label icon and create the new meta-release label: "camara-<meta-release name>" e.g. camara-fall25,  camara-spring26, etc.
  • Remove the non-applicable timeline 
  • Remove the non-applicable milestone dates table
  • if the dates need to be adjusted, the source PPT of the meta-release schedule is attached to this page: RM templates to copy
    • picture display size = 960px and middle size.
  • In the "API version status" section, update the macro adding a filter using the newly created meta-release label 
  • Then remove these red lines.

Timeline


image-2024-4-11_16-42-56.pngImage RemovedImage Added


Image RemovedImage Added

Milestone dates

MilestoneTarget dateStatusActual date
M009-30

kick-off preparation

 

M1 (Commonalities & ICM)10-15

M2 (Commonalities & ICM)12-3107

M3 (API Sub-projects)12-1521

M4 (API Sub-projects)02-28

M503-15

M603-31

...

Milestone

Target dateStatusActual date
M003-31

kick-off preparation

 

M1 (Commonalities & ICM)04-15

M2 (Commonalities & ICM)06-1507

M3 (API Sub-projects)06-1521

M4 (API Sub-projects)08-30

M509-15

M609-30

...