For the schedule and content of actual planned meta-releases, see CAMARA meta-releases.
Meta-release
...
milestones
Meta-release milestones and their associated actions are used to progress and track the status of the meta-release.
...
- Commonalities, ICM: release tracking and milestone activities
- API Sub Projects: release tracking and milestone activities
- Release Management: meta-release tracking and milestone activities
- TSC: milestone activities
Milestone / start date | Actors & Activities for next milestone | Timeline | Week Nr |
---|---|---|---|
pre-M0 |
| ||
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 |
| 2 weeks | |
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 |
| 7 weeks | |
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 |
| 9 weeks | |
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 |
| 9 weeks | |
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API |
| 2 weeks | |
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 |
| 2 weeks | |
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
Processes
All CAMARA teams play their part in the meta-release process. The actions are listed An overview of the activities per team is shown in the above milestone table.
Additional information The details on the actions activities for all teams each team can be found in the below process descriptions:
- The process to manage a meta-release is described here: Meta-release Process
- The process for the Commonalities and ICM teams is described here: Commonalities and ICM release process
- Details on releasing an API version and the related API versioning are described here: API Release Process.
...