Working Group

Commonalities

ICM

Target scope

Commonalities/issues/175

IdentityAndConsentManagement/issues/146

Public release date (M2)

2024-08-23

2024-08-22

Public release tag

r0.4.0

r0.2.0

Timeline

Fall meta-release schedule
Plantuml
title
Plantumlcloud
toolbarbottom
filenamespring.svg
originalHeight270
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
compressedtrue
originalWidth584
revision1

Release History

Milestone status

Milestone

Target date

Status

Actual date

Comment

M0

04-15 04-18

kick-off done

2024-04-18

 

M1 (Commonalities & ICM)

04-30 05-15 05-31 06-15 06-10

Commonalities: alpha available

ICM: alpha / M1 skipped

2024-06-10

M1 was declared to be for Commonalities only by the TSC on 2024-07-04.

M2 (Commonalities & ICM)

06-15 07-15 07-10

Commonalities: release PR ready

ICM: release PR ready

2024-07-11

Commonalities 0.4.0-rc.1 and ICM 0.2.0-rc.1 - approved on 2024-07-10.

ICM 0.2.0-rc.2 released on 2024-08-01

M3 (Sub Projects)

07-15 07-21 07-26 (08-10) 08-15

Preparation of first release-candidates by M3 (through one or more alpha API versions as needed)

2024-08-15

Prepare your release PR by this date and have it reviewed by the Release Mgmt team before merging.

Last submission date for M3 review: Aug 10th (for approval by Aug 15th)

M4 (Sub Projects)

08-30 09-11

M4 APis to be release after RM approval when ready

2024-09-11

APIs that passed M3 (or submitted for approval) can start to prepare their public release PR for M4.

M5

09-15

Delivered


Preparation of the final meta-release page

M6

09-30



Feedback provided is being incorporated.