Instructions:
When copying this page for the planning of a new meta-release:
In the page title, change <meta-release name> to the actual meta-release name (e.g. Fall25, Spring26, etc).
At the top of the page, click the label icon and create the new meta-release label: "camara-<meta-release name>" e.g. camara-fall25, camara-spring26, etc.
Remove the text above the applicable timeline figure
Remove the non-applicable
timeline timeline figure and text above it
Remove the non-applicable milestone dates table
if If the dates need to be adjusted
: here are , edit the
source pictures -picture display size = 960px and middle size.PlantUML source of the timeline figure.
In the "API version release status" section, update the macro by adding the newly created meta-release label in the "Labels" section
In the "API version release review status" section, update the macro by adding the newly created meta-release label in the "Labels" section
In the "API release contacts" section, update the macro by adding
a filter using the newly created meta-release
label label in the "Labels" section
Then remove these red lines.
Table of Contents |
---|
Timeline
...
Spring meta-release schedule
Plantumlcloud | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Fall meta-release schedule
Plantumlcloud | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Milestone status
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 09-30 |
kick-off preparation |
|
| ||
M1 (Commonalities & ICM) | 10-15 | |||
M2 (Commonalities & ICM) | 12- |
07 | |||
M3 (Sub Projects) | 12- |
21 | ||||
M4 (Sub Projects) | 02-28 | |||
M5 | 03-15 | |||
M6 | 03-31 |
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 03-31 |
kick- |
off preparation |
|
|
M1 (Commonalities & ICM) | 04- |
15 | |||
M2 (Commonalities & ICM) | 06- |
07 | |||
M3 (Sub Projects) | 06- |
21 | |||
M4 (Sub Projects) | 08- |
31 | ||||
M5 | 09-15 | |||
M6 | 09-30 |
Commonalities & ICM
This section is to be updated by the Commonalities and ICM working groups respectively.
Working Group | Commonalities | ICM |
---|---|---|
Target version |
0.5.0 | 0.3.0 |
Target scope |
<shortened issue link> | <shortened issue link> | |
(Pre-)release tag | <shortened release tag link> | <shortened release tag link> |
M1 date | yyyy-mm-dd | yyyy-mm-dd |
M2 date | yyyy-mm-dd | yyyy-mm-dd |
Public-release tag |
<shortened release tag link> |
<shortened release tag link> | ||
M5 date | yyyy-mm-dd | yyyy-mm-dd |
Patch date | yyyy-mm-dd | yyyy-mm-dd |
API version release status
Below are the API release trackers as proposed of the API versions presented by the API Sub -projects Projects for this meta-release.
In the The below table , all data is automatically pulled from the API Sub-project owned API release trackers owned by the Sub Projects.
The individual API release tracker is the link trackers are in the first column called "API version".
Page Properties Report | |||
---|---|---|---|
|
...
|
...
|
...
|
...
|
...
|
...
|
...
|
API version release review status
Page Properties Report | ||||||||
---|---|---|---|---|---|---|---|---|
|
API release contacts
Page Properties Report | ||||||||
---|---|---|---|---|---|---|---|---|
|