TO BE ARCHIVED

Review closed (2024-04-30) - approved content move to Meta-release Milestones page. - this page is kept to resolve comments and will be archived.

UPDATED PROPOSAL FOR REVIEW (2024-04-23)

Please review the table on this page - proposal is that it replaces the table on the Meta-release Milestones page.


Milestone / start date

Actors & Actions for next milestone

Timeline

Week Nr

pre-M0

Release Management

  • Prepare meta-release page
  • Request TSC to declare kickoff

Commonalities & ICM (from previous M2)

  • Prepare release scope definition for meta-release.
  • Implement scope in one or more alpha releases

TSC

  • Declare meta-release kickoff


M0 

Meta-release kickoff

M00
starts @ M0

Release Management

  • Send kick-off message to all@lists.camaraproject.org
  • Check release-candidate PRs Once available, check the final alpha release of Commonalities & ICM and, if OK, submit to TSC for approval
  • After TSC approval, announce M1 milestone

Commonalities & ICM

  • Define the scope for meta-release.
    • Record scope in dedicated GitHub issue.
    • Submit scope issue for TSC review
  • Develop Commonalities & ICM scope through one or more alpha release(s)releases
  • Update data in the meta-release plan with each alpha release
  • Create first release-candidate (x.y.z-rc.1) PR and final alpha release PR and submit to Release Management
  • After TSC approval: , create approved first release-candidate of final alpha release for Commonalities & ICM
  • Update the meta-release plan with the alpha release tag

TSC

  • Approve final alpha release -candidate PRs of Commonalities & ICM
2 weeks

M1

Release-candidate Alpha Commonalities & ICMM0 + 2 weeks2
starts @ M1

Commonalities & ICM

  • Fix bugs raised by users through one or more release-candidates
  • Update release tracker on meta-release page with each release-candidate
  • Create publicfinal release-release candidate PR and submit to Release Management
  • After TSC approval:
    • Create the publicfinal release-release PR candidate for Commonalities & ICM
    • Update the meta-release page for Commonalities & ICM with publicrelease-release candidate tag

Release Management

  • Check publicfinal release-release candidate PRs of Commonalities and ICM and, if OK, submit to TSC for approval
  • After TSC approval, and commit of Commonalities and ICM final release-candidate PRs, announce M2 milestone

TSC

  • Approve public-release PR final release-candidate PRs of Commonalities & ICM
10 7 weeks

M2

Public-release Commonalities & ICMM1 + 10 weeks

12

M1

Release-candidate Commonalities & ICMM0 M1 + 2 7 weeks29
starts @ M1

API Sub-projects

  • Create API release tracking page for the API if it does not yet exist
  • Create API release tracker for the API version to be released
  • Define scope of API release:
    • Record scope in dedicated GitHub issue.
    • Submit scope for TSC review
    • Update the release tracker with the scope issue link
  • Develop API scope through one or more alpha release(s)
  • Update the API release tracker with each alpha release
  • Create first release-candidate (x.y.z-rc.1) PR and submit to Release Management
  • After TSC Release Management approval:
    • Create first release-candidate (x.y.z-rc.1) for the API
    • Update the API release tracker with the release-candidate tag

Release Management

Check

, for each API

  • Once available, check the API release-candidate PR and, if OK, submit to TSC for approval
  • If OK, approve creation of first release-candidate
  • If NOK, or in case of questions, notify TSC for checking the API release-candidate PR
  • Announce M3 milestone when with all API alpha releases are reviewed by TSCapproved API release-candidates.

TSC

  • Review proposed API release-candidate PR
8
  • PRs on request of Release Management and approve (or reject)
9 weeks

M3

Release-candidate APIs (Code Freeze)

M1 + 8 9 weeks

109
starts @ M3

API Sub-projects

  • Fix bugs raised by API testers through one or more release-candidates
  • Update API release tracker with each release-candidate
  • Submit public-release PR to Release Management for checking
  • After TSC approval:
    • Create API public-release (x.y.z)
    • Update the API release tracker with public-release tag

Release Management

  • Check Once available, check API public-release PR and, if OK, submit to TSC for approval
  • Announce M4 milestone when all API public-releases are approved by TSC

TSC

  • Approval of API public-release PR for all proposed
  • API Sub-project
  • APIs
10 9 weeks

M4

Public-release APIs

M3 + 10 9 weeks

2018

starts @ public-release PR for an API

Release Management

  • Check that all API release trackers are updated for the meta-release
  • Propose meta-release content to TSC
  • After TSC approval, publish the meta-release
  • Announce the M5 meta-release on all@lists.camaraproject.org 

TSC:

  • Meta-release approval
2 weeks

M5

Meta-releaseM4 + 2 weeks2220
starts @ M5

Release Management

  • Review release process with all teams and identify areas for improvement. 
  • Propose improvements for TSC approval

TSC

  • Meta-release improvements approval.
2 weeks

M6

Post Release AssessmentM5 + 2 weeks24

...