Instructions:
When copying this page for the planning of a new meta-release:
In the page title, change <meta-release name> to the actual meta-release name (e.g. Fall25, Spring26, etc).
At the top of the page, click the label icon and create the new meta-release label: "camara-<meta-release name>" e.g. camara-fall25, camara-spring26, etc.
Remove the text above the applicable timeline figure
Remove the non-applicable
timeline timeline figure and text above it
Remove the non-applicable milestone dates table
if If the dates need to be adjusted, edit the PlantUML source
PPT of the meta-release schedule is attached to this page: RM templates to copypicture display size = 960px and middle size.of the timeline figure.
In the "API version release status" section, update the macro by adding the newly created meta-release label in the "Labels" section
In the "API version release
contactsreview status" section, update the macro by adding the newly created meta-release label in the "Labels" section
In the "API
version statusrelease contacts" section, update the macro by adding the newly created meta-release label in the "Labels" section
Then remove these red lines.
Table of Contents |
---|
Timeline
...
Spring meta-release schedule
Plantumlcloud | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Fall meta-release schedule
Plantumlcloud | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Milestone status
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 09-30 | kick-off preparation |
|
|
M1 (Commonalities & ICM) | 10-15 | |||
M2 (Commonalities & ICM) | 12-07 | |||
M3 (Sub Projects) | 12-21 | |||
M4 (Sub Projects) | 02-28 | |||
M5 | 03-15 | |||
M6 | 03-31 |
Milestone | Target date | Status | Actual date | Comment |
---|---|---|---|---|
M0 | 03-31 | kick-off preparation |
|
|
M1 (Commonalities & ICM) | 04-15 | |||
M2 (Commonalities & ICM) | 06-07 | |||
M3 (Sub Projects) | 06-21 | |||
M4 (Sub Projects) | 08- |
31 | ||||
M5 | 09-15 | |||
M6 | 09-30 |
Commonalities & ICM
This section is to be updated by the Commonalities and ICM working groups respectively.
Working Group | Commonalities | ICM |
---|---|---|
Target version |
0.5.0 | 0.3.0 | |
Target scope | <shortened issue link> | <shortened issue link> |
(Pre-)release tag | <shortened release tag link> | <shortened release tag link> |
M1 date | yyyy-mm-dd | yyyy-mm-dd |
M2 date | yyyy-mm-dd | yyyy-mm-dd |
Public-release tag | <shortened release tag link> | <shortened release tag link> |
M5 date | yyyy-mm-dd | yyyy-mm-dd |
Patch date | yyyy-mm-dd | yyyy-mm-dd |
API version release status
Below are the API release trackers of the API versions presented by the Sub Projects for this meta-release.
The below table is automatically pulled from the API release trackers owned by the Sub ProjectProjects.
The individual API release trackers are in the first column called "API version".
Page Properties Report | |||
---|---|---|---|
|
...
|
...
|
...
|
...
|
...
|
API version release review status
Page Properties Report | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
|
API release contacts
Page Properties Report | ||||||||
---|---|---|---|---|---|---|---|---|
|
...
|