More details on these activities for each team are documented in the section on planning and progress tracking for a meta-release.
- Commonalities and ICM: release tracking and milestone activities
- API Sub Projects: release tracking and milestone activities
- Release Management: meta-release tracking and milestone activities
- TSC: milestone activities
Details on releasing an API version and the related API versioning are described here: API Release Process.
...
Milestone / start date | Actors & Activities for next milestone | Timeline | Week Nr |
---|---|---|---|
pre-M0 activities |
| ||
M0 | Meta-release kickoff | M0 | 0 |
activities for M1 start @ M0 |
| 2 weeks | |
M1 | Alpha release Commonalities & ICM | M0 + 2 weeks | 2 |
activities for M2 start @ M1 |
| 7 weeks | |
M2 | Release candidate Commonalities & ICM | M1 + 7 weeks | 9 |
activities for M3 start @ M1 |
| 9 weeks | |
M3 | Release candidates for APIs (Code Freeze) | M1 + 9 weeks | 9 |
activities for M4 start @ M3 |
| 9 weeks | |
M4 | Public releases of APIs | M3 + 9 weeks | 18 |
activities for M5 starts @ public - release PR for an API |
| 2 weeks | |
M5 | Meta-release | M4 + 2 weeks | 20 |
activities for M6 start @ M5 |
| 2 weeks | |
M6 | Post Meta-release Assessment | M5 + 2 weeks | 24 |
...
The "typical" meta-release schedule for Spring and Fall meta-releases are depicted in the below figures. NOTE: Actual dates for a given meta-release shall be managed on the dedicate meta-release plan which are listed here: CAMARA meta-releases.
be managed on the dedicated meta-release plans which are listed here: CAMARA meta-releases.
Plantumlcloud | ||||||||
---|---|---|---|---|---|---|---|---|
|
Plantumlcloud | ||||||||
---|---|---|---|---|---|---|---|---|
|
Release contacts
Meta-releases are administered and tracked by
...
- M0
- Announce the meta-release kick-off on the CAMARA mailing list (all@lists.camaraproject.org). This announcement indicates:
- the Commonalities and ICM teams to prepare for M1 the scope definition of what they plan to put in the meta-release
- all API Sub Projects to create the API release tracker for their next planned API version(s) as described here: API release trackers.
- the Outreach Committee to start preparation of marketing activities based on information in the meta-release plan
- Once available, check the final alpha releases PR of Commonalities & ICM and their release asset availability. If OK, submit to TSC for approval.
- After TSC approval, announce M1 on release management and maintainers mailing lists.
- Announce the meta-release kick-off on the CAMARA mailing list (all@lists.camaraproject.org). This announcement indicates:
- M1
- Check for Commonalities and ICM that all release assets are available in their final release - candidate PRs.
- If OK, request TSC to approve creation of the final release - candidate of Commonalities and ICM.
- After TSC approval, and update of the meta-release plan with the final release - candidate tags of Commonalities and ICM, announce M2 milestone.
- M2
- From M1, for all APIs, once available, check the first API release - candidate PR and, if OK, approve PR.
- Announce M3 milestone once all approved API release - candidates have update their API release tracker.
- M3
- For all APIs, once available, check final API release - candidate PR and, if OK, approve PR. Approval can start as soon as an API Sub Project indicates "M4: ready for RM" on the API release tracker in the comments field. It is not necessary to wait for the actual M4 date if an API release is ready before.
- For all APIs, once available, check API public - release PR, and, if OK, ask for formal TSC approval.
- Announce M4 milestone when all API public - releases are approved by TSC.
- M4
- Check that all API release trackers are updated with their public - release tag for the meta-release.
- Propose meta-release content to TSC.
- After TSC approval, publish the meta-release.
- Announce the M5 meta-release on all@lists.camaraproject.org
- M5
- Review the release process with all teams and identify areas for improvement for the next meta release with all teams. A meta-release feedback page is available to all to add comments, feedback and suggestions for improvement. I
- Propose improvements for TSC approval to TSC to be implemented for the next meat-release.
- After TSC approval, announce M6 milestone
- M6
...
Milestone | Before milestone | After milestone |
---|---|---|
M0 | kick-off preparation | kick-off done |
M1 | alpha PR | alpha for M2 |
M2 | release - candidate PR | release - candidate for M4 |
M3 | API first release - candidate PR | API first release - candidate for M4 |
M4 | API final release - candidate PR API public - release PR | API final release - candidate API public - release for M5 |
M5 | meta-release preparation | meta-release published |
M6 | retrospective preparation | retrospective done |
...
Field | Field explanation | When to update |
---|---|---|
Target version | the public release version targeted for the meta-release | at M0 or when the target scope issue is created |
Target scope | link to GitHub issue defining the release scope | when the issue is created |
M1 / date | date of pre-release or actual final alpha release milestone date | when each alpha release is created |
M2 / date | date of pre-release or actual final release candidate milestone date | when each release candidate is created |
(Pre)release tag | link to latest pre-release (alpha or release candidate) | when a new pre-release is created |
M5 / date | actual final public release milestone date | when the public release is created |
Public - release tag | link to final public release tag | when the public release is created |
...
- M0
- Start following the scope definitions of Commonalities and ICM and assess impact on API version
- M1
- Create API release tracking page for the API if it does not yet exist (it is normally created as part of the API Sub Project creation)
- Create API release tracker for the API version to be released
- Assess impact of alpha release of Commonalities and ICM scope on API(s)
- Define scope of API release:
- Record scope in dedicated GitHub issue.
- Update the release tracker with the link to the scope issue
- Develop API scope through one or more alpha releases
- Update the API release tracker with each alpha release tag
- Create first release - candidate PR and submit to Release Management
- After Release Management approval:
- Create first release candidate for the API
- Update the API release tracker with the release candidate tag
- M3
- Fix bugs raised by API testers through one or more release candidates
- Update API release tracker with each release candidate tag
- Submit final release candidate PR to Release Management for checking
- After final release candidate PR approval by Release Management:
- Create final release candidate and update API release tracker with its tag
- Create API public release PR
- After TSC approval of the PR
- Create public release
- Update the API release tracker with public release tag
- M4
- N/A
- M5
- Provide feedback on meta-release
- M6
...