Date

Attendees & Representation

...

  • Meta-release Fall-24 - timeplan updated
    • https://wikilf-camaraproject.camaraprojectatlassian.orgnet/wiki/display/CAM/Meta-release+Fall24
    • Expected Deliverables 
      • M0 - approved, but communication delayed (expected begin of next week)
      • M1 - 30/04
        • Scope of Commonalities finalised: 
        • Scope of ICM in work, focus on OIDC profile
        • The release process definition expects here already an alpha release of Comm & ICM, but they will come only later, at latest 2 weeks before the release candidates (for review by API Sub Projects)
      • M2 - 15/06
        • (Release candidate of Commonalities + ICM)
      • M3 - 15/06
        • First release candidate of DeviceLocation, starting of test implementations
      • M4 - 31/08
        • Last (stable) release candidate of target release from DeviceLocation
        • Release Criteria fulfilled (incl validation of the release candidate by two independent implementation of the API)
      • M5 - 15/09
        • public release done

...

...

Implementation

Define guidelines for geofencing implementation

...