For the schedule and content of actual planned meta-releases, see CAMARA meta-releases.
Meta-release
...
milestones
Meta-release milestones and their associated actions are used to progress and track the status of the meta-release.
...
More details on these for each team are documented here:
- Commonalities, ICM: release tracking and milestone activities
- API Sub Projects: release tracking and milestone activities
- Release Management: meta-release tracking and milestone activities
- TSC: milestone activities
Milestone / start date | Actors & Activities for next milestone | Timeline | Week Nr |
---|---|---|---|
pre-M0 activities |
| ||
M0 | Meta-release kickoff | M0 | 0 |
activities for M1 start @ M0 |
| 2 weeks | |
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
activities for M2 start @ M1 |
| 7 weeks | |
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
activities for M3 start @ M1 |
| 9 weeks | |
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
activities for M4 start @ M3 |
| 9 weeks | |
M4 | Public-release APIs | M3 + 9 weeks | 18 |
activities for M5 starts @ public-release PR for an API |
| 2 weeks | |
M5 | Meta-release | M4 + 2 weeks | 20 |
activities for M6 start @ M5 |
| 2 weeks | |
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
Processes
All CAMARA teams play their part in the meta-release process. The actions are listed An overview of the activities per team is shown in the above milestone table.
Additional information The details on the actions activities for all teams each team can be found in the below process descriptions:
- The process to manage a meta-release is described here: Meta-release Process
- The process for the Commonalities and ICM teams is described here: Commonalities and ICM release process
- Details on releasing an API version and the related API versioning are described here: API Release Process.
...