Timeline
Meta-release milestone dates
The possible status values are described in the Milestone release status section on the following page: CAMARA Release Process.
Milestone | Target date | Status | Actual date |
---|---|---|---|
M0 | 15/04 | scope definition |
|
M1 | 30/04 | ||
M2 | 15/06 | ||
M3 | 15/06 | ||
M4 | 31/08 | ||
M5 | 15/09 | ||
M6 | 30/09 |
Commonalities & ICM status
Each Working Group shall update the line to the below for the version they plan to release at the M0 date.
In the below table,
- Milestone dates shall be updated with the actual dates on which the milestone is achieved.
- The link in the Current version release package column shall be updated with each milestone to point to the associated latest release package.
Working Group | Target version | Target scope | M0 date | M1 date | M2 date | M5 date | Pre-release tag | Public-release package |
---|---|---|---|---|---|---|---|---|
Commonalities | <link> | <link> | ||||||
ICM | <link> | <link> |
API version status
Each API Sub-project shall create and maintain a release tracker page for each API version they are working on and planning to release.
In the below table,
- Milestone dates shall be updated by each API development team with the actual dates on which the milestone is achieved.
- The links shall be updated with each milestone to point to the associated latest tag or release package.