2025-04-01 Release WG Minutes
ย
Community Attendees:
@Rafal Artych @Surajj Jaggernath @Samuel Adeyemo @Tanja de Groot
Community Attendees:
LF Staff:
@Casey Cain
Agenda
Antitrust Policy
The project's Antitrust Policy is linked from the LF and project websites. The policy is important when multiple companies, including potential industry competitors, are participating in meetings. Please review it, and if you have any questions, please contact your companyโs legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.
Action Items Review
Spring25 meta-release
Fall25 meta-release
Issues review
AOB
Minutes
Action Items Review
See action items list here: Release Management Working Group
For test statement - give a reminder at the TSC for teams to fill their Test statements by 29 april.
Versioning updates in Commonalities: proposal to be done once the new structure of the guidelines is available by Commonalities call -14 April.
Spring25 meta-release (Spring25)
M6
Release Management public release was done (r2.2, v0.3.0)
target date: Apr 1, 2025 + email codeowners, rm lists
Fall25 meta-release (https://lf-camaraproject.atlassian.net/wiki/x/FQApAg?atlOrigin=eyJpIjoiZWIyZGY3YWY4Yzk2NGQxNWFjODlkZGNmYmFmYTVkMDIiLCJwIjoiYyJ9)
M0
preparation to be done - target date is TSC meeting on April 3rd
M1
Target date: April 15th
Commonalities: proposed to shift to April 29th
Document restructuring needs some more time
Scope issue is being prepare in issue #423 : error updates / subscriptions/notifications
@Rafal Artych to update the Fall25 page
for M2 public release, the plan is to also include generation of artefacts for testing / linting
ICM: scope issue #275 is ongoing
Issues review
Issues ยท camaraproject/ReleaseManagement
Test result statement for stable APIs within Spring25 meta-release (M4) ยท Issue #161 ยท camaraproject/ReleaseManagement - target date for closure: Apr 29, 2025
AOB
Next week meeting: 17-18 CEST / 15-16 UTC is good - April 8th