2025-04-08 Release WG Minutes
Community Attendees:
@Rafal Artych @Herbert Damker @Tanja de Groot @Surajj Jaggernath
Community Attendees:
LF Staff:
@Casey Cain
Agenda
The project's Antitrust Policy is linked from the LF and project websites. The policy is important when multiple companies, including potential industry competitors, are participating in meetings. Please review it, and if you have any questions, please contact your company’s legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.
Action Items Review
Spring25 meta-release
Fall25 meta-release
Issues review
AOB
Minutes
Action Items Review
See action items list here: Release Management Working Group
Reminder was given at the TSC meeting for teams to fill their Test statements by 29 april.
Versioning updates in Commonalities: proposal to be done once the new structure of the guidelines is available by Commonalities call -14 April.
Spring25 meta-release (Spring25)
M6
Email sent to codeowners, rm lists on M6 announcement. Spring25 is now officially closed.
Fall25 meta-release (https://lf-camaraproject.atlassian.net/wiki/x/FQApAg?atlOrigin=eyJpIjoiZWIyZGY3YWY4Yzk2NGQxNWFjODlkZGNmYmFmYTVkMDIiLCJwIjoiYyJ9)
M0
kick-off done in TSC meeting on April 3rd.
Fall25 M0 announcement email sent to all after (non-quorum) OK by TSC meeting + of-line approval by Herbert.
M1
Target date: April 15th, proposed to shift to April 29th in the TSC on April 3rd.
There was no quorum in that TSC meeting, but no opposition from the people present. It was decided to put the decision to the next TSC meeting on April 17th.
Commonalities:
Document restructuring needs some more time
Scope issue #423 is ongoing: error updates / subscriptions/notifications; further work (not impacting APIs (e.g. linting) well be done for M2)
@Rafal Artych to update the Fall25 page (version to be updated to 0.6.0)
ICM 0.4.0: scope issue #275 is ongoing, Fall25 page has been updated with that issue.
Release Management to update its Confluence and GitHub artefacts for the Fall25 (alpha release at M1)
Issues review
Fall24: patch update of SimSwap - need to complete the last point on the reveiw issue
Issues · camaraproject/ReleaseManagement
https://github.com/camaraproject/ReleaseManagement/issues/200
Identify when in the process to deliver the API description
Format to be discussed (should allow copy-paste, or other transfer)
Add item to the review issue
SimSwap r1.4 (Fall24 Patch) release review · Issue #199 · camaraproject/ReleaseManagement
Public release information updated
@Herbert Damker to complete these pointsin GitHub README
on CAMARA website
within API Backlog list
Test result statement for stable APIs within Spring25 meta-release (M4) · Issue #161 · camaraproject/ReleaseManagement - target date for closure: Apr 29, 2025
AOB
API backlog - update with actual releases - PR #194 - can be reviewed