<meta-release name> meta-release

<meta-release name> meta-release

Instructions:

When copying this page for the planning of a new meta-release:

  • In the page title, change <meta-release name> to the actual meta-release name (e.g. Fall25, Spring26, etc).

  • Save the page

  • At the bottom of the page, click the “add label” button and create the new meta-release label: "camara-<meta-release name in lower case>" e.g. camara-spring26, camara-fall26, etc.

  • Edit the page as follows:

    • Remove the non-applicable timeline figure and text above it

    • Remove the non-applicable milestone dates table

    • If the dates need to be adjusted, edit the PlantUML source of the timeline figure.

    • In the "API version release status" section, update the macro to use the new meta-release label in the "Labels" section

    • In the "API version release review status" section, update the macro to use the new meta-release label in the "Labels" section

    • In the "API release contacts" section, update the macro to use the new meta-release label in the "Labels" section

    • Then remove these red lines.

Timeline

Spring meta-release schedule

Fall meta-release schedule

Milestone status

Milestone

Target date

Status

Milestone

Target date

Status

M0

sep 30

kick-off preparation

M1 (Commonalities & ICM)

oct 15



M2 (Commonalities & ICM)

dec 07



M3 (Sub Projects)

dec 21



M4 (Commonalities & ICM)

feb 14

 

M4 (Sub Projects)

feb 28



M5

mar 5



M6

mar 31







Milestone

Target date

Status

Milestone

Target date

Status

M0

mar 31

kick-off preparation

M1 (Commonalities & ICM)

apr 15



M2 (Commonalities & ICM)

jun 07



M3 (Sub Projects)

jun 21



M4 (Commonalities & ICM)

aug 15

 

M4 (Sub Projects)

aug 31



M5

sep 15



M6

sep 30