2025-10-07 Release WG Minutes
Community Attendees:
@Alberto Ramos Monaga @Rafal Artych @Tanja de Groot
Community Attendees:
LF Staff:
@Casey Cain
Agenda
The project's Antitrust Policy is linked from the LF and project websites. The policy is important when multiple companies, including potential industry competitors, are participating in meetings. Please review it, and if you have any questions, please contact your company’s legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.
Action Items Review
Discussion Review
Fall25 meta-release
Spring26 meta-release
Release schedule update
Issues review - Release Management
Issues review - CAMARA Project Administration (repository)
AOB
Minutes
Approval of previous meeting’s minutes: comments from Herbert are for discussion in this meeting - approved
Action Items Review
See action items list here: https://lf-camaraproject.atlassian.net/wiki/spaces/CAM/pages/14552660
Issue #273 and PR #275 reviews delayed due to new RM schedule discussions.
Discussions Review
See camaraproject/ReleaseManagement · Discussions · GitHub: No new discussion.
Fall25 meta-release (https://lf-camaraproject.atlassian.net/wiki/x/FQApAg?atlOrigin=eyJpIjoiZWIyZGY3YWY4Yzk2NGQxNWFjODlkZGNmYmFmYTVkMDIiLCJwIjoiYyJ9)
M6
release cycle cadence change proposal: see below section on Release schedule update
release-management repo release - Should be done before merge of any PR with changes for Spring26 … just to have checkpoint what was valid for Fall25 (comment from Herbert) - Agreed @Tanja de Groot to create the release PR and related info
automation proposal is for review (CAMARA Release workflow and metadata proposal - PR #257)
Spring26 meta-release (https://lf-camaraproject.atlassian.net/wiki/x/AQB_Cg)
M0
M0 was declared in last week’s TSC meeting. See 2025-10-02 TSC Minutes - CAMARA Project - CAMARA Project
M1
delayed from Oct 15. alpha and release-candidate (M2) release dates to be determined.
Commonalities and ICM are preparing content for Spring26
Use the scope issue to the define the milestones
M1 APIs
Start work against the Fall25 Commonalities and ICM releases (r3.3)
Release schedule update
New meta-release schedule proposal following the feedback in Dual Phase proposal: see
SECOND DRAFT: v2 Updated meta-release plan - CAMARA Project - CAMARA Project - still WIP
Proposal v2 - feedback:
Release Management proposal is ready for the steady state case.
Spring26 and Fall26 adjusted schedule for the transition period based on the following assumptions:
no new APIs to be release in Spring26, focus is on Comm/ICM release only.
initial APIs can still create a release at any time and ask for review: they should use the Fall25 Comm/ICM release until the public version of Comm/ICM of Spring26 is available.
Fall25 API should plan to prepare updates for Fall26 based on Comm/ICM of Spring26.
proposed adjusted schedules for Spring26 (Comm/ICM) and Fall26 APIs are also available - see SECOND DRAFT above.
New meta-release naming : please check & comment https://github.com/camaraproject/Governance/issues/200 .
Issues review - Release Management
See Issues · camaraproject/ReleaseManagement - progress is logged in the issues
not reviewed
Issues review - CAMARA Project Administration (repository)
repository link: project-administration
no new issues
AOB
CAMARA Webinar instead of AHC this week - please promote