Sync26 meta-release (ex-Fall26)

Sync26 meta-release (ex-Fall26)

Timeline

Sync26 meta-release schedule (transition period)

 

 

APIs should preferably target the Sync26 meta-release, and align with Spring26 Commonalities and ICM.

Milestone status

Milestone

Target date

Status

Milestone

Target date

Status

M1 (Commonalities & ICM)

nov 30

from Spring26

M0

jan 15

kick-off preparation

M2 (Commonalities & ICM)

jan 31 feb 15 feb 19

from Spring26

M4 (Commonalities & ICM)

mar 15 mar 22 apr 15 apr 30 may 19 may 21

from Spring26

M1 (API Sub Projects)

apr 30 may 31

Passed

M3 (API Sub Projects)

jun 15 jun 30 jul 31 aug 31 sep 15 oct 06/16 oct 20

M3 was declared on oct 20. APIs that have not passed M3 will be routed to the independent track to continue their release process.

M4 (API Sub Projects)

oct 31

Date revised to fit shift in M3; All APIs should have created their rc with Commonalities r4.4 by oct 16 before public release.

M5

nov 07

Date revised to fit shift in M4

M6

nov 15

 

Commonalities & ICM

The Commonalities and ICM releases to be used in the Sync26 meta-release are released in Spring26.

API version release status

The following table presents the progress of the APIs of the meta-release (for the repositories that have adopted the automated release management process).

To adopte the process, API projects need to include the release-plan.yaml in their repository through the proposed “Bulk” PR. To reflect the release intent for Sync26, at least include the meta-release Sync26 and the API name(s), then merge the PR. If no other changes are made, the API will be shown with Release State “None”. The target release and other info in the plan can be done later through normal PRs when the team has made their decisions.