2026-07-24 Connectivity Quality Management Minutes
Community Attendees:
Herbert Damker Ben Hepworth Randy Levensalor Eric Murray Toshi Wakayama Masaharu Hattori Rafal Artych
Community Attendees:
Jose Luis Urien Pinedo Rafal Artych
LF Staff:
Agenda
The project's Antitrust Policy is linked from the LF and project websites. The policy is important when multiple companies, including potential industry competitors, are participating in meetings. Please review it, and if you have any questions, please contact your company’s legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.
General
DedicatedNetworks (@Thorsten Lohmar, @Hubert Przybysz, @Stefano Brivio)
QualityOnDemand (@Herbert Damker, @Randy Levensalor, @Jose Luis Urien Pinedo, @Eric Murray)
QoSBooking (@Masaharu Hattori, @Jose Luis Urien Pinedo)
AOB
Minutes
Previous Meeting Minutes
General Sub Project Topics
CQM new repositories (Herbert Damker )
Sync26 Timeplan and release process
M3 date on July 31
As communicated within AHC on July 9th and confirmed in TSC on July 16th
M3 milestone requires the first RC pre-release for Sync26
M4 milestone is on September 30th, which means that there is time until roughly mid of September to create further release candidates if there is the need for fixes etc.
Dashboard of Release Progress (updated once every 24 hours): https://camaraproject.github.io/ReleaseManagement/progress.html
Alignment/Adaptation to latest Commonalities release (r4.3 - Spring26)
Relevant for all APIs in the three repositories
Expectation is that ALL errors and warnings from validation are addressed (or exceptions documented) and refs$ used
Heads-up: a r4.4 will come in August, providing some smaller fixes and changes of Commonalities.
Whitepaper (from last minutes):
Timing: Whitepaper release with the Sync26 release
Draft for review is ready: https://github.com/camaraproject/ConnectivityQualityManagement/blob/main/documentation/SupportingDocuments/CQM API Introduction.md
Comments can already be provided
Walkthrough of the paper at August 7th, then regular discussion of review comments/questions in CQM meetings (standing agenda item)
Review until September 4th or 18th, with formal finalization of the paper
Publishing/announcement probably on OSS in Prague 7-9 October
New Issue in CQM: 429 QUOTA_EXCEEDED usage in DN and QOS B&A · Issue #16 · camaraproject/ConnectivityQualityManagement
no update
DedicatedNetworks
https://github.com/camaraproject/DedicatedNetworks/issues/69
Specifically for the second release candidate: https://github.com/camaraproject/DedicatedNetworks/issues/135
Merged since last meeting
Open PRs
https://github.com/camaraproject/DedicatedNetworks/pull/137
New snapshot after #136, RM re-review done, smaller issues still open
New and not yet addressed issue in scope of Sync26
https://github.com/camaraproject/DedicatedNetworks/issues/139
https://github.com/camaraproject/DedicatedNetworks/issues/138
https://github.com/camaraproject/DedicatedNetworks/issues/134
https://github.com/camaraproject/DedicatedNetworks/issues/131
https://github.com/camaraproject/DedicatedNetworks/issues/130
https://github.com/camaraproject/DedicatedNetworks/issues/129
QualityOnDemand
Merged since last meeting
Open PRs
https://github.com/camaraproject/QualityOnDemand/pull/580
final fixes pushed by Jose Luis Urien Pinedo, ready for final review
https://github.com/camaraproject/QualityOnDemand/pull/575
ready for final review
New or not yet addressed issues (not) in scope of Sync26
https://github.com/camaraproject/QualityOnDemand/issues/577
PR - to be created by Eric Murray , if possible before the rc.1
QoSBooking
Merged since last meeting
none
Open PRs
https://github.com/camaraproject/QoSBooking/pull/109
RM review done, new issues opened by Tanja De Groot (Nokia) and Herbert Damker
Q (Masaharu Hattori): when is it expected to fix the issues? Some of them could be fixed short-term, but other need discussion within the team, won’t be possible before the deadline. A (Herbert Damker): cheap and obvious fixes would be good to be done before the rc.1, but decision is with the team.
New and not yet addressed issue in scope of Sync26
https://github.com/camaraproject/QoSBooking/issues/114
Could be also beyond the the scope of Sync26 in a next minor version, tbd
AOB
Documentation updates (issues created by Marketing team in the repositories) - from last minutes
Update the wiki pages with the source of the API descriptions with the requested changes, e.g. for QoS Booking and Assignment update the page https://lf-camaraproject.atlassian.net/wiki/x/IYA5Cg
Use the opportunity also to do any other necessary updates
The marketing team plans to update the API descriptions on the website based on the input on wiki until Sync26 meta-release, including new pictures created by LF creative team.
Next meetings:
Next regular CQM: August 7th
Dedicated Networks Breakout: check schedule with @Thorsten Lohmar
CQM Breakout – API Alignment: check schedule with @Thorsten Lohmar