NEW PROPOSAL
Milestone / start date | Actors & Activities for next milestone | Timeline | Week Nr |
---|
pre-M0 | - Release Management: prepare meta-release plan
- Commonalities & ICM: define scope and start alpha release development
- TSC: declare M0 - meta-release kickoff
|
|
|
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | - Commonalities & ICM: fix scope and develop final alpha release for M1
- API Sub Groups: check Commonalities and ICM scope definition to assess API impact
- TSC: approve Commonalities and ICM scope and final alpha release
- Release Management: Declare M1 - Commonalities and ICM alpha release available
| 2 weeks |
|
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | - API Sub Groups: align to Commonalities and ICM alpha release and provide feedback
- Commonalities & ICM: Fix bugs and prepare final release-candidate for M2
- TSC: approve Commonalities and ICM final release-candidate
- Release Management; declare M2 - Commonalities and ICM release-candidate available
| 7 weeks |
|
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 | - API Sub Projects: prepare API scope and develop alpha releases, ending by the first release-candidate for M3
- TSC: review scope of APIs (case by case selection)
- Release Management: check API readiness of each API and declare M3 - all API first release-candidates available
| 9 weeks |
|
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 | - API Sub Projects: fix bugs and prepare public-release
- Commonalities & ICM: prepare public-release
- Release Management: check API readiness of each API and declare M4 - all API public-releases available
- TSC: give formal approval of Commonalities, ICM and API (case-by-case) public-releases
| 9 weeks |
|
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API | - Release Management: prepare and announce M5 - meta-release availability
- TSC: approve meta-release
| 2 weeks |
|
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 | - Release Management: assess process and prepare meta-release improvement plan and declare M6
- TSC: Approve improvement plan for M6
| 2 weeks |
|
M6 | Post Release Assessment | M5 + 2 weeks | 24 |
ORIGINAL TABLE
Milestone / start date | Actors & Actions for next milestone | Timeline | Week Nr |
---|
pre-M0 | Release Management - Prepare meta-release page
- Request TSC to declare kickoff
Commonalities & ICM - Starting from previous M2, prepare scope definition for upcoming meta-release.
- Implement scope in one or more alpha releases
TSC - Declare meta-release kickoff
|
|
|
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | Release Management - Announce M0 meta-release kick-off on all@lists.camaraproject.org
- Once available, check the final alpha releases PR of Commonalities & ICM and, if OK, submit to TSC for approval
- After TSC approval, announce M1 milestone
Commonalities & ICM - Finalize the scope definition for meta-release.
- Record scope in dedicated GitHub issue.
- Submit scope issue for TSC review
- Develop final Commonalities & ICM scope through one or more alpha releases
- Update data in the meta-release plan with each alpha release
- Create final alpha release PRs and submit to Release Management
- After TSC approval, create approved final alpha release for Commonalities & ICM
- Update the meta-release plan with the alpha release tag
API Sub Projects - Start following the scope definitions of Commonalities and ICM and assess impact on API version
TSC - Approve Commonalities and ICM scope
- Approve final alpha release PRs of Commonalities & ICM
| 2 weeks |
|
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | Commonalities & ICM - Fix bugs raised by users through one or more release-candidates
- Update release tracker on meta-release page with each release-candidate
- Create final release-candidate PR and submit to Release Management
- After TSC approval:
- Create the final release-candidate for Commonalities & ICM
- Update the meta-release page for Commonalities & ICM with release-candidate tag
Release Management - Check final release-candidate PRs of Commonalities and ICM and, if OK, submit to TSC for approval
- After TSC approval, and commit of Commonalities and ICM final release-candidate PRs, announce M2 milestone
TSC - Approve final release-candidate PRs of Commonalities & ICM
| 7 weeks |
|
M2 | Release-candidate Commonalities & ICM | M1 + 7 weeks | 9 |
starts @ M1 | API Sub Projects - Create API release tracking page for the API if it does not yet exist
- Create API release tracker for the API version to be released
- Assess final impact of final release-candidates of Commonalities and ICM scope on API(s)
- Define scope of API release:
- Record scope in dedicated GitHub issue.
- Update the release tracker with the scope issue link
- Develop API scope through one or more alpha releases
- Update the API release tracker with each alpha release
- Create first release-candidate PR and submit to Release Management
- After Release Management approval:
- Create first release-candidate for the API
- Update the API release tracker with the release-candidate tag
Release Management, for each API - Once available, check the first API release-candidate PR and, if OK, approve PR
- Announce M3 milestone with all approved API release-candidates.
TSC - Review scope of selected APIs (case by case selection)
| 9 weeks |
|
M3 | Release-candidate APIs (Code Freeze) | M1 + 9 weeks | 9 |
starts @ M3 | API Sub Projects - Fix bugs raised by API testers through one or more release-candidates
- Update API release tracker with each release-candidate
- Submit final release-candidate PR to Release Management for checking
- After final release-candidate PR approval by Release Management:
- Create final release-candidate and update API release tracker
- Create API public-release PR
- After TSC approval of the PR
- Create public-release
- Update the API release tracker with public-release tag
Release Management, for each API - Once available, check final API release-candidate PR and, if OK, approve PR
- Once available, check API public-release PR, and, if OK, ask for formal TSC approval.
- Announce M4 milestone when all API public-releases are approved by TSC
Commonalities & ICM (through M3 upto M4) - Fix bugs raised by API testers through one or more release-candidates
- Create public-release PR for Commonalities & ICM
- After Release Management check and TSC approval of the public-release PR
- Create the public-release
- Update the meta-release page with public-release tag
TSC - Formal approval of the Commonalities & ICM public-release PRs
- Formal approval API public-release PRs
| 9 weeks |
|
M4 | Public-release APIs | M3 + 9 weeks | 18 |
starts @ public-release PR for an API | Release Management - Check that all API release trackers are updated with their public-release tag for the meta-release.
- Propose meta-release content to TSC
- After TSC approval, publish the meta-release
- Announce the M5 meta-release on all@lists.camaraproject.org
TSC: | 2 weeks |
|
M5 | Meta-release | M4 + 2 weeks | 20 |
starts @ M5 | Release Management - Review release process with all teams and identify areas for improvement.
- Propose improvements for TSC approval
- After TSC approval, announce M6 milestone
TSC - Provide feedback on meta-release
- Meta-release improvements approval.
| 2 weeks |
|
M6 | Post Release Assessment | M5 + 2 weeks | 24 |