WIP
UPDATE PROPOSAL
LATEST move milestone name to Actions column
Milestone / start date | Actors & Actions for next milestone | Timeline | Week Nr |
---|---|---|---|
pre-M0 | Release Management
Commonalities & ICM (from previous M2)
TSC
| ||
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | Release Management (before M0)
Commonalities & ICM
TSC
| 2 weeks | |
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | Commonalities & ICM
TSC
| 10 weeks | |
M2 | Release-candidate Commonalities & ICM | M1 + 10 weeks | 12 |
starts @ M1 | API Sub-projects
TSC
| 8 weeks | |
M3 | Alpha APIs | M1 + 8 weeks | 10 |
starts @ M3 | API Sub-projects
TSC
| 10 weeks | |
M4 | Release-candidate APIs | M3 + 10 weeks | 20 |
starts @ M2 for Commonalities & ICM starts @ public-release PR for an API | Release Management (this can start for each item, whenever the item public-release PR is made available)
TSC:
Commonalities & ICM
API Sub-projects
| 2 weeks | |
M5 | Meta-release | M4 + 2 weeks | 22 |
starts @ M5 | Release Management
TSC
| 2 weeks | |
M6 | Post Release | M5 + 2 weeks | 24 |
ORIGINAL
Milestone | Milestone Name | Actions to achieve milestone | Timeline | Week number |
---|---|---|---|---|
Kickoff - M0 | Start of release cycle. | M0 | 0 | |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week | 2 |
M2 | Finalize Commonalities & ICM |
| M1 + 10 weeks | 12 |
M3 | Initiate Sub-projects / APIs |
| M1 + 8 weeks | 10 |
M4 | Finalize Sub-projects / APIs |
| M3 + 10 weeks | 20 |
M5 | Meta Release |
| M4 + 2 weeks | 22 |
M6 | Post- Release |
| M5 + 2 weeks | 24 |
(back to 1 column for actions) add actor and split groups of actions per actore
Milestone | Actors & Actions for next milestone | Timeline | Week Nr |
---|---|---|---|
M0 - meta-release kickoff | M0 | 0 | |
Release Management
Commonalities & ICM
TSC
| 2 weeks | ||
M1 - Draft Commonalities & ICM | M0 + 2 weeks | 2 | |
Commonalities & ICM
TSC
| 10 weeks | ||
M2 - Final Commonalities & ICM | M1 + 10 weeks | 12 | |
API Sub-projects
TSC
| 8 weeks | ||
M3 - Draft APIs | M1 + 8 weeks | 10 | |
API Sub-projects
TSC
| 10 weeks | ||
M4 - Final APIs | M3 + 10 weeks | 20 | |
Release Management
| 2 weeks | ||
M5 - Meta Release | M4 + 2 weeks | 22 | |
Release Management
| 2 weeks | ||
M6 - Post Release | M5 + 2 weeks | 24 |
ORIGINAL
Milestone | Milestone Name | Actions to achieve milestone | Timeline | Week number |
---|---|---|---|---|
Kickoff - M0 | Start of release cycle. | M0 | 0 | |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week | 2 |
M2 | Finalize Commonalities & ICM |
| M1 + 10 weeks | 12 |
M3 | Initiate Sub-projects / APIs |
| M1 + 8 weeks | 10 |
M4 | Finalize Sub-projects / APIs |
| M3 + 10 weeks | 20 |
M5 | Meta Release |
| M4 + 2 weeks | 22 |
M6 | Post- Release |
| M5 + 2 weeks | 24 |
Insert separate milestone lines
Milestone | Milestone Name | Actions to achieve next milestone | Timeline | Week number |
---|---|---|---|---|
Kickoff - M0 | Start of release cycle. | M0 | 0 | |
| 2 weeks | |||
M1 | Initiate Commonalities & ICM | M0 + 2 weeks | 2 | |
| 10 weeks | |||
M2 | Finalize Commonalities & ICM | M1 + 10 weeks | 12 | |
| 8 weeks | |||
M3 | Initiate Sub-projects / APIs | M1 + 8 weeks | 10 | |
| 10 weeks | |||
M4 | Finalize Sub-projects / APIs | M3 + 10 weeks | 20 | |
| 2 weeks | |||
M5 | Meta Release | M4 + 2 weeks | 22 | |
| 2 weeks | |||
M6 | Post- Release | M5 + 2 weeks | 24 |
separate action in 2 columns (but would need a 3rd for RM actions)
Milestone | Milestone Name | Actions Commonalities & ICM | Actions API Sub-projects | Timeline | Week Nr |
---|---|---|---|---|---|
Kickoff - M0 | Start of meta-release | M0 | 0 | ||
| 2 weeks | ||||
M1 | Initial Commonalities & ICM | M0 + 2 weeks | 2 | ||
| 10 weeks | ||||
M2 | Final Commonalities & ICM | M1 + 10 weeks | 12 | ||
| 8 weeks | ||||
M3 | Initial Sub-projects / APIs | M1 + 8 weeks | 10 | ||
| 10 weeks | ||||
M4 | Final Sub-projects / APIs | M3 + 10 weeks | 20 | ||
| 2 weeks | ||||
M5 | Meta Release | M4 + 2 weeks | 22 | ||
| 2 weeks | ||||
M6 | Post Release | M5 + 2 weeks | 24 |
merge milestone and milestone name columns
Milestone | Actions Commonalities & ICM | Actions API Sub-projects | Timeline | Week Nr |
---|---|---|---|---|
M0 - meta-release kickoff | M0 | 0 | ||
| 2 weeks | |||
M1 - Initial Commonalities & ICM | M0 + 2 weeks | 2 | ||
| 10 weeks | |||
M2 - Final Commonalities & ICM | M1 + 10 weeks | 12 | ||
| 8 weeks | |||
M3 - Initial Sub-projects / APIs | M1 + 8 weeks | 10 | ||
| 10 weeks | |||
M4 - Final Sub-projects / APIs | M3 + 10 weeks | 20 | ||
| 2 weeks | |||
M5 - Meta Release | M4 + 2 weeks | 22 | ||
| 2 weeks | |||
M6 - Post Release | M5 + 2 weeks | 24 |