CAMARA release management process requires each API Sub Project to plan and track their API releases so that the meta-release can be planned.
For each API version that is planned to be released by an API Sub Project, an API release tracker needs to be created to track its planning and progress through the release process.
The following sections provide the details.
Sub Project API release tracking (umbrella page)
All API release trackers are located under the release tracking page of the API Sub Project (note: this page title has "tracking", not "tracker" which is for one API version !).
The API release tracking page is the place where an API Sub Project documents the releases of all its API version(s).
This umbrella page has been created in all Sub Project wikis under the home page. (It is part of the Sub Project creation template).
If the page is missing, you can create it manually as follows:
- Go to the following page <API Sub Project name> API Release Tracking, and create a copy indicating your API Sub Project home page as the target parent page.
- Replace the <API name> in the copied page title with the API repository name.
The is the umbrella page under which all API release trackers of the API Sub Project will be hosted.
Examples
The following are examples of API Sub Projects with their umbrella release tracking page and sample API release trackers:
- EXAMPLE: API Sub Project with one API
- EXAMPLE: API Sub Project with multiple APIs - this example has one release tracking page for all 3 APIs.
Create an API release tracker for an API release
For each new release of an API (e.g. at M0), a dedicated API release tracker (page) is created to plan and track the progress of that API release.
To create an API release tracker, go to the API Sub project's release tracking page (as described in the previous section) and do the following:
- Push the "Add API release tracker" button to create the tracker page for the new API release.
- In the page title, put the <API name> and a "v" followed by the <Target version> as described in the below table, e.g. geofencing v1.0.0
- Complete the table on the page following the indications in the table below. PLEASE DO NOT CHANGE THE FIRST COLUMN.
- If planned for meta-release, add the meta-release label to the page (e.g. camara-fall24)
- Maintain the page up-to-date to reflect the progress of the API version through the release process.
NOTE: The API release tracker is a normal confluence page. The API Sub Project can add any additional information about the API version as they see useful.
API release tracker content
Each API release tracker has the below table that serves as the source for tracking progress of the release of the API version.
In particular, this content is pulled into the meta-release planning page (based on the page meta-release label).
IMPORTANT
The left column of this table shall not be changed. If you want to add a new field, please contact the release management team through the mailing list to request the addition of the field and the reason to add it. Adding a field will require a manual update to ALL release tracker pages.
Explanations:
Meta-release | The name of the meta-release, e.g. Fall24. Put N/A if the API version is planned to be an initial public release only outside of the meta-release. |
API name | The API name. See the definition of API name on this page: API Release Process, e.g. geofencing |
Group | The name of the GitHub repository for the API Sub Project, e.g. DeviceLocation |
Repository | The shortened link to GitHub repository for the API Sub Project, e.g. DeviceLocation |
Target version | The API version that you plan to publish in the indicated meta-release, e.g. 1.0.0 |
Target scope | The shortened link to a GitHub issue called "Scope for target version" which needs to be created latest at M1 and resolved by M3 e.g. DeviceLocation/issues/58 |
Target maturity | Indicates the maturity of the API version that is targeted in the upcoming meta-release: choose one of initial / stable. |
Readiness checklist | The shortened link to the API readiness checklist for the API. The template of the checklist can be found here: (link to release management repo tbd) |
M3 date | The date when the first release-candidate API version is ready. This is the starting point for creating the final release-candidate API version for M4. After this date, only bug fixes and necessary non-breaking changes can be made to the API. Format is yyyy-mm-dd |
M4 date | The date when the final release-candidate API version for M5 submission is ready. This is the starting point for creating the public-release API version for M5. Once this date is provided by the API project team, the Release Management team can check the release-candidate API version for acceptance and submit to the TSC for approval. Format is yyyy-mm-dd |
API version | The version of the latest pre-release (alpha or release-candidate) API version to be updated at M3 and M4 date, e.g. 0.2.0_alpha.3, 0.10.0-rc.2, 0.10.1, 1.0.0-rc.5) |
pre-release tag | The shortened release tag of the latest pre-release (alpha or release-candidate) for the API version e.g. QualityOnDemand/releases/tag/r0.10 |
M5 date | The date by which the Release Management team has checked the release-candidate API version provided at the M4 date and the API is approved by the TSC. The link to the PR for public-release API version shall be included in this field when available After this date, if approval is obtained, the API Sub Project shall commit the PR of the public-release API version and its release assets for use in the meta-release. Format is yyyy-mm-dd. The link to the PR shall be removed after the commit is done. |
public-release tag | The shortened release tag of the public-release API version. This field is updated once the public-release has been created, e.g. QualityOnDemand/releases/tag/r1.0 |
Comments | Field for exchanging information with RM team, for example M3: alpha ready for RM M3: checked by RM - NOK - missing sunny test cases M4: ready for RM M4: ready for approval by TSC M4: approved by TSC M5: public-release done M5: API version retirement planned by yyyy-mm-dd. |
Contacts | Contact names for the API release: name1 @name2 |
API release tracker template v4 (actual: v3)
This is the baseline for the Confluence template for API release tracker pages (to be used only by Confluence Admin to copy to the template page).
Start of template (please copy the below red lines up to and including the last line of this page to the template):
If planned for the meta-release, add the meta-release label to the page by clicking on the label icon at the top of the page and adding "camara-<meta-release name>", e.g. camara-fall24, camara-spring25, etc.
Remove these lines in red.
Additional Information