Event name, link, number of participantsScheduleLocationProgress Overview
Microsoft BUILD05/21Seattle / onlineSee detailed steps below
Vivatech05/22-05/25ParisPresentation Only
TOA06/04-06/07BerlinPresentation Only
DTW Ignite06/18-06/20CopenhagenSee detailed steps below
Open Telco LATAM Summit06/26-06/27virtualPresentation Only
MWC Shanghai06/26-06/28ShanghaiSee detailed steps below
CAMARA webinar06/xx and 07/xxvirtual

Pending updates from Domos/Magnus Olden

WeAreDevelopers World Congress07/17-07/19Berlin
Infobip Shift09/16-09/17Zadar

Presentation Only

Open Source Summit Europe09/16-09/18Vienna
CASA 2409/16-09/18Amsterdam
API Days London09/18-09/19LondonPresentation Only
Digital-X09/18-09/19Cologne

See detailed steps below

MWC Las Vegas10/08-10/10Las Vegas

See detailed steps below

KubeCon + CloudNativeCon NA11/12-11/15Salt Lake City

See detailed steps below

Microsoft Ignite11/18-11/22Seattle & online

Awaiting confirmation

AWS Re:invent12/02-12/06Las Vegas

Awaiting cost estimate

API Days Paris12/03-12/05ParisPresentation Only

Event Progress Tracking:

All next steps to be updated for accuracy by event owner.

Microsoft Build

Date: 5/21

Owner: Ricardo/Markus

Next StepsDetailsStatusDate
Confirm pre-recorded session speaker


Confirm session speaker


Record APC session


Draft presentation script


Finalize presentation script


Submit/send pre-record session to correct point of contact


DTW Ignite Copenhagen

Date: 6/18-6/20

Owner: Markus

Next StepsDetailsStatusDate
Sign contract (Confirm details of space, location, layout, etc.)


Order catering


Finalize any physical marketing materials


Finalize any additional logistical items


Spread the word of the meet & greet


MWC Shanghai

Date: 6/26-6/28

Owner: Lucy/Markus

Next StepsDetailsStatusDate
Confirm which member booths will run CAMARA presentations


Finalize 'DevCon' program


Finalize panel/presentation participants 


Finalize speaker content


Send out marketing materials


WeAreDevelopers World Congress

Date: 7/17-7/19

Owner: Mario/Markus

Next StepsDetailsStatusDate
Create concept 


Align concept with partners (CAMARA, Open Gateway, DT, Orange, Telefonica, Vodafone)


Sign contract


Add next steps once concept is created...


OpenSource Summit Europe Vienna

Date: 9/16-9/18

Owner: Jill/Markus

Next StepsDetailsStatusDate
Sign contractSigned for booth - 8kComplete-
Submit CFP2 submittedComplete4/30
CFP Notifications

6/11
Finalize booth design details


Finalize swag/Order any swag


Build presentation for 'accepted' CFP



Digital-X

Date: 9/18-9/19

Owner: Markus

Next StepsDetailsStatusDate
Create concept 


Align concept with partners (CAMARA, Open Gateway, DT, Orange, Telefonica, Vodafone)


Sign contract


Add next steps once concept is created...



MWC Vegas

Date: 10/8-10/10

Owner: Lucy/Markus

Next StepsDetailsStatusDate
Confirm which member booths will run CAMARA presentations


Finalize 'DevCon' program


Finalize panel/presentation participants 


Finalize speaker content


Send out marketing materials



KubeCon North America

Date: 11/12-11/15

Owner: Alicia/Markus

Next StepsDetailsStatusDate
Submit CFP3 submitted CFPsComplete6/9
Decide on sponsorshipSilver PackageIn progress8/1
Discuss hackathon/sponsorship options

Operators to participate? What does the hackathon look like? What has been done previously?

Sales team offering silver sponsorships to LF projects at 50% discount. Silver would be $14k (10x10 booth, 6 conference passes)

In progress - review at 6/18 outreach committee meeting6/18
CFP NotificationsLF will provide status on 3 CFPs
8/12
Sign contractLast day to sign contractNot started8/16
Hackathon Planning-Not Started-
Finalize booth design detailsPending sponsorship confirmation Not Started-
Finalize swag/Order any swag2k BudgetedNot Started-
Build presentation for 'accepted' CFPPending acceptanceNot Started-


Presence TypeDescription/DetailsCritical MilestoneMilestone Date
Booth Establish presence in developer centric area to engage meaningfully

Discuss presence at outreach committee meeting

Sign contract

Finalize booth layout

Submit graphics                    

6/18

8/16

TBD

HackathonShowcase to the community real world examples and use cases 

Confirm operator participation

Validate hackathon

TBD
CFP

Establish broad presence through speaking engagement

Operators to participate? What does the hackathon look like? What has been done previously?

Sales team offering silver sponsorships to LF projects at 50% discount. Silver would be $14k (10x10 booth, 6 conference passes)

Submit CFPs(3)

CFP Notification

Organize panelists/create materials

6/9

8/12

TBD

MarketingHighlight CAMARA's presence - pre event, during event, and post event

Print any materials

Send out email blast 

Order swag

Post on LinkedIn

TBD
  • No labels