5Community Attendees:
Community Attendees:
LF Staff:
Agenda
DRAFT
Antitrust Policy
Action Items Review
Spring25 meta-release
Issues review
AOB
Minutes
Action Items Review
See previous minutes: 2025-02-11 Release WG Minutes
On issue: Update of versioning guidelines for the url field · Issue #405 · camaraproject/Commonalities: proposed solution was to include full version number in url for alpha and release-candidate APIs.
Has been applied in Spring25 by OTPvalidation and NumberVerification
Issues were opened:
Discussion was reopened for Fall25
Spring25 meta-release
13 new APIs and 22 updated Fall24 APIs (of 25) are candidate for Spring25. Total of 35 APIs in 19 API repositories
Two Sub Projects decided to skip the Spring25 and go to Fall25:
dedicated-networks, as still under design
simple-edge-discovery which will take the time to do a redesign to better align with CAMARA guidelines.
Some APIs were moved to Sandboxed APIs (APIs not yet in any meta-release)
M2
Commonalities 0.5.0 public release PR (WIP): Release 2.3 · Pull Request #419 - RM reveiw to e done when ready.
ICM 0.3.0 public release PR is available: Spring25 Public Release r2.3 · Pull Request #269 - RM approval was given
Note: Public release target: Feb 14 (2 weeks before M4)
M3
5 API reviews remaining (see Issues review below)
WebRTC was published without RM approval but will still be reviewed. to be discussed.
Finale decisions will be made at TSC on Feb 20.
M4
Feb 28th
M5
March 15: target date for M5. is OK for input to marketing.@
@ Plan to create an update of the marketing slides (technical part on release mgmt)
Issues review
Issues · camaraproject/ReleaseManagement
AOB
Updated text for camaraproject.org website: please see Release Management Working Group description
The result is visible here Release Management – Camara Project (still need the fix from “Sandbox” to “Sandboxed”).