Meta-release Spring25
Timeline
Milestone status
Milestone | Target date | Status | Actual date |
---|---|---|---|
M0 | 09-30 10-03 | kick-off to be pronaounced by TSC on Oct 3rd | ย |
M1 (Commonalities & ICM) | 10-15 10-31 11-07 | TSC has declared M1 on Nov 7th. Exception for Spring25 M1: Comm. & ICM alpha are not yet available by this date, but the set of PRs are available as described in the below scope issues. API Sub Projects are to review these PRs. A second M1 announcement will follow when the alpha releases will be available. | |
M2 (Commonalities & ICM) | 12-07 12-06 | Release Management decision to declare M2 with the available alpha releases which include all changes impacting API definitions. Sub Projects can work for their M3 with the available alpha releases. | |
M3 (Sub Projects) | 12-21 01-17 01-24 | New date approved at TSC on Jan 16th: M3 shifts to 2025-01-24, the cut-off date for API release PRs for Spring25 release. Requires the availability of API release tracker and review issue for the API. | |
M4 (Sub Projects) | 02-28 | ||
M5 | 03-15 | ||
M6 | 03-31 |
Commonalities & ICM
This section is updated by the Commonalities and ICM working groups respectively.
Working Group | Commonalities | ICM |
---|---|---|
Target version | 0.5.0 | 0.3.0 |
Scope | ||
Pre-release | ||
M1 date | 2024-12-06 | 2024-12-03 |
Latest public-release | <short release tag / PR# link> | <short release tag / PR# link> |
M2 date | yyyy-mm-dd | yyyy-mm-dd |
Patch date | ย | ย |
API version release status
This section lists the API release trackers as proposed by the Sub Projects for this meta-release.
In the below table, all data is automatically pulled from the API release trackers owned by the Sub Projects.
The individual API release tracker is the link in the first column called "Target API version".
ย