Updated table of CAMARA Release Process
WIP
The first table on this page - proposal is that it replaces the table on CAMARA Release Process page.
The tables below it are the ORIGINAL and other attempts, so-far not-retained reformatting of the table.
LATEST move milestone name to Actions column
Milestone / start date | Actors & Actions for next milestone | Timeline | Week Nr |
|---|---|---|---|
pre-M0 | Release Management
Commonalities & ICM (from previous M2)
TSC
|
|
|
M0 | Meta-release kickoff | M0 | 0 |
starts @ M0 | Release Management (before M0)
Commonalities & ICM
TSC
| 2 weeks |
|
M1 | Alpha Commonalities & ICM | M0 + 2 weeks | 2 |
starts @ M1 | Commonalities & ICM
TSC
| 10 weeks |
|
M2 | Release-candidate Commonalities & ICM | M1 + 10 weeks | 12 |
starts @ M1 | API Sub-projects
TSC
| 8 weeks |
|
M3 | Alpha APIs | M1 + 8 weeks | 10 |
starts @ M3 | API Sub-projects
TSC
| 10 weeks |
|
M4 | Release-candidate APIs | M3 + 10 weeks | 20 |
starts @ M2 for Commonalities & ICM starts @ public-release PR for an API | Release Management (this can start for each item, whenever the item public-release PR is made available)
TSC:
Commonalities & ICM
API Sub-projects
| 2 weeks |
|
M5 | Meta-release | M4 + 2 weeks | 22 |
starts @ M5 | Release Management
TSC
| 2 weeks |
|
M6 | Post Release | M5 + 2 weeks | 24 |
ORIGINAL
Milestone | Milestone Name | Actions to achieve milestone | Timeline | Week number |
|---|---|---|---|---|
Kickoff - M0 | Start of release cycle. |
| M0 | 0 |
M1 | Initiate Commonalities & ICM |
| M0 + 2 week | 2 |
M2 | Finalize Commonalities & ICM |
| M1 + 10 weeks | 12 |
M3 | Initiate Sub-projects / APIs |
| M1 + 8 weeks | 10 |
M4 | Finalize Sub-projects / APIs |
| M3 + 10 weeks | 20 |
M5 | Meta Release |
| M4 + 2 weeks | 22 |
M6 | Post- Release |
| M5 + 2 weeks | 24 |
(back to 1 column for actions) add actor and split groups of actions per actore
Milestone | Actors & Actions for next milestone | Timeline | Week Nr |
|---|---|---|---|
M0 - meta-release kickoff |
| M0 | 0 |
| Release Management
Commonalities & ICM
TSC
| 2 weeks |
|
M1 - Draft Commonalities & ICM |
| M0 + 2 weeks | 2 |
| Commonalities & ICM
TSC
| 10 weeks |
|
M2 - Final Commonalities & ICM |
| M1 + 10 weeks | 12 |
| API Sub-projects
TSC
| 8 weeks |
|
M3 - Draft APIs |
| M1 + 8 weeks | 10 |
| API Sub-projects
TSC
| 10 weeks |
|
M4 - Final APIs |
| M3 + 10 weeks | 20 |
| Release Management
| 2 weeks |
|
M5 - Meta Release |
| M4 + 2 weeks | 22 |
| Release Management
| 2 weeks |
|
M6 - Post Release |
| M5 + 2 weeks | 24 |
ORIGINAL
Milestone | Milestone Name | Actions to achieve milestone | Timeline | Week number |
|---|---|---|---|---|
Kickoff - M0 |